Q:A construction firm and a school have a 10 page contract on page 3 it says no price increase if materials go up but on page 8 it says room for price increase based on materials do you follow page 3 or page 8
A:You might think based on our גמרא that you follow the bottom page 8 but nowadays it is different contracts are typed on a computer and printed out the change in terms b/4 page 8 printed fixed 3 forgot about page 8 page 3 wins school does not pay for price increase in materials